Indian Point Unit 2 Will Continue Operating Under Its Existing NRC License, Providing Essential, Clean and Affordable Power with Continuing NRC Oversight until the License Renewal Process is Complete, as Provided by Well-Established Federal Law

Indian Point Unit 2 Will Continue Operating Under Its Existing NRC License, Providing Essential, Clean and Affordable Power with Continuing NRC Oversight until the License Renewal Process is Complete, as Provided by Well-Established Federal Law


Indian Point safely and reliably provides approximately 25 percent of New York City’s and Westchester County’s electricity, with virtually no carbon emissions and at lower cost than most alternatives. Its continued operation is a vital component of the region's economic and environmental future.

NRC Staff has recommended that the licenses for the two operating units at Indian Point be renewed for an additional 20 years of operation, saying the plants can be operated safely and that there are no environmental impacts that would preclude license renewal.

Entergy Will Continue Safely Operating and NRC will Continue Oversight


  • Entergy has taken steps to ensure that Indian Point, which remains subject to all NRC safety requirements, continues operating safely while the license renewal process continues.
  • The NRC will continue its extensive reactor oversight and inspection programs.
  • Additionally, NRC Staff is completing inspections of the plant’s license renewal commitments before September 28th.

Regulatory Basis for Continued Operation of Indian Point Unit 2


  • Federal law and NRC regulations permit continued operation of IP2 beyond its original licensing period. The current operating license remains in full force and effect. IP2’s original license would have expired on Sept. 28, 2013.
  • Entergy filed an application for license renewal of both Indian Point Units 2 and 3 in April 2007, more than five years ahead of IP2’s original expiration date of Sept. 28, 2013, satisfying the requirements of the Timely Renewal Doctrine (IP3’s license expires on Dec. 12, 2015).
  • By law, the current operating license is extended until the license renewal process is complete.
  • The Timely Renewal Doctrine was established by the federal Administrative Procedures Act. It is incorporated into NRC regulations and has been applied by the NRC in other licensing matters.

The Indian Point License Renewal Process is Continuing


  • NRC personnel have performed more than 28,000 work-hours of inspections and reviews.
  • The license renewal application continues under review by the NRC and is the subject of an ongoing adjudicatory proceeding before the independent Atomic Safety and Licensing Board.
  • NRC Staff issued an Environmental Impact Statement in 2010 and a Safety Evaluation Report in 2009. In June of this year NRC issued a Supplemental Environmental Impact Statement regarding endangered aquatic species. Additional supplements are possible.
  • A final NRC determination on license renewal for Indian Point is not expected for several years.

Timely Renewal is Well-Established Federal Law with a Long History


The timely renewal doctrine is a well-established rule of law generally applicable to administrative agencies. Two examples of operation under timely renewal include: A federal district court held that an EPA discharge permit for a paper company remained effective for almost 20 years due to hearing delays and bureaucratic inefficiencies. And FERC held that an existing hydroelectric license held by a utility remained in effect despite a state board’s denial of a Section 401 water quality certification and pending appeal.