| State Consultant
Reiterates: Indian Point Plan Is Weak
By RANDAL C. ARCHIBOLD
The New York Times
March 7, 2003
After hearing from a range of individuals, government officials
and institutions, a consultant hired by the state has reaffirmed
his warning that emergency plans for the Indian Point nuclear
power plant cannot protect the public from a large release
of radiation.
The consultant, James Lee Witt, a former director of the
Federal Emergency Management Agency, plans the release today
of his final report, which defends and clarifies some points
in his original report but does not change his primary conclusion.
"The comments that addressed major, substantive issues
were not sufficiently compelling that the draft's major findings,
conclusions, and recommendations needed to be changed in the
final report," according to an excerpt from the final
report provided to The New York Times in response to inquiries.
Mr. Witt's report, which predicted that an evacuation could
be hampered by panicked residents clogging roads, emergency
workers unwilling or unable to respond and other uncertainties
and problems, energized a campaign by citizens groups, environmentalists
and elected leaders to close the plant, 35 miles north of
Midtown Manhattan in the Westchester village of Buchanan,
N.Y.
The report motivated members of Congress to hold hearings
and other forums on the emergency plan, which includes steps
for evacuating people within a federally mandated 10-mile
radius of the plant. Congress has ordered the Federal Emergency
Management Agency to respond to the report by March 25.
The concerns it raised were cited by the four counties surrounding
the plant and by New York State in the decision not to sign
off on the emergency plan this year. FEMA in turn has given
the state until May 2 to submit updated information on the
plan it has sought for months. Without that information, the
agency has said, it will officially reject the plan, leaving
the fate of the plant to the Nuclear Regulatory Commission,
which requires plants to have a FEMA-endorsed plan.
"We have made observations that we believe will benefit
the citizens of the state of New York and we have made them
in the hope that that potential benefit might be realized,"
Mr. Witt said in a statement.
Mr. Witt's consulting firm, James Lee Witt Associates, collected
72 submissions from the public between Jan. 10, when it released
the report, and Feb. 7. It originally intended to release
the final version on Feb. 28, but delayed it to further analyze
the reponses, a spokeswoman said.
Entergy Corp., which owns the plant, has disputed several
points in the report, but the final report says that "few
changes in the draft were required due to factual errors."
But one of seven points the report chose to clarify is an
assertion Entergy has been making for the past several weeks.
"We make no assertions that a terrorist attack would
cause a faster or larger release," the report says, going
on to explain that it had brought up the issue of a larger
release only because officials thought that it was theoretically
possible and that the plan did not adequately address it.
On another point, however, the final report disagrees with
Entergy's past statements that the plant and the plan could
adequately address a large release, regardless of its cause.
"There are unique aspects of a terrorist-caused incident
that should be considered in planning and exercise,"
the report says. It adds that the plan does not take into
account the possibility that the plant would be declared a
crime scene after a terrorist attack and that the presence
of federal law enforcement officers might affect how an emergency
response was carried out.
"Existing plans should be followed during an emergency,"
the report says. "Our intent was not to discredit the
plans, but to improve them."
This week, the Nuclear Regulatory Commission said in its
annual assessment of Indian Point that while Entergy had improved
the safety performance of Indian Point 2, extra scrutiny would
still be given because of lingering problems.
The N.R.C. said that there was a backlog of repairs to be
done and that it wanted to give additional tests to control
room operators, a number of whom had failed exams in 2001,
though they passed exams last year. It said Entergy also needed
to continue improving security. Precautions were beefed up
after 9/11 but have been criticized by some guards as inadequate
for a terrorist attack.
Indian Point 3, the N.R.C. said, was running well, though
the commission raised similar security concerns there.
|