| New Indian Pt.
Cooling System: Years in the Making, and More to Come
By LISA W. FODERARO
The New York Times
November 14, 2003
A day after New York State laid out rigorous requirements
for the Indian Point nuclear plant that were intended to reduce
fish kills, environmentalists and other critics disputed the
plant owner's claims that a new cooling system would cost
more than $1 billion.
Entergy Nuclear Northeast, the owner of the plant in Westchester
County, said a "closed-cycle" cooling system, which
would reduce fish mortality by 97 percent, could be so expensive
as to cause it to close the plant.
On one level, that is precisely what plant opponents would
like to see. But the environmental groups and the state legislator
who sued the State Department of Environmental Conservation
to compel the installation of a new cooling system say that
they were not motivated by a desire to see the plant shut
down.
Rather, long before Sept. 11, 2001, and the concerns about
the plant's vulnerability to terrorism, environmental groups
were pushing the federal government and then the state to
force Indian Point to install a new cooling system. Such a
system would use recycled water and avoid sucking in up to
2.5 billion gallons of water a day from the Hudson River,
killing millions of fish and their eggs and larvae each year.
The environmental group Riverkeeper — a party to the
lawsuit against the state brought last year by Assemblyman
Richard L. Brodsky, the singer Pete Seeger and others —
said that over a year, Indian Point's current cooling system
withdrew the equivalent of the entire volume of the river
from Battery Park to Troy, N.Y.
Riverkeeper's predecessor, the Hudson River Fishermen's Association,
along with the Natural Resources Defense Council and Scenic
Hudson, have worked for 30 years to get Indian Point and other
nonnuclear power plants along the Hudson to adopt closed cooling
systems.
In fact, the Environmental Protection Agency, in its enforcement
of the Clean Water Act, issued a similar draft permit in 1975
calling for the same kind of cooling technology the state
recommended on Wednesday.
Years of hearings followed that draft permit; then the issue
was formally delayed for 10 years, beginning in 1981. That
was the year the groups signed a landmark agreement with several
utilities and state and federal agencies that, among other
things, stopped a fiercely contested pumped storage plant
that Con Edison wanted to build on Storm King Mountain north
of West Point, N.Y.
In exchange for the withdrawal of that proposal, the environmental
groups and the regulators agreed that the utilities did not
have to install the newer cooling technology for 10 years.
After 1991 came more studies and negotiations but no action,
and Indian Point was allowed to operate its present cooling
system even after its permit expired.
So while environmental groups and Mr. Brodsky applauded the
state's move this week, they focused even more on what they
saw as a lax timetable for implementation, possibly as long
as a decade.
Under the draft permit, which will enter a 90-day comment
period, Entergy would not have to build a cooling system until
it received a license extension from the Nuclear Regulatory
Commission. The license for one of the plant's reactors expires
in 2013, while the other expires in 2015. Entergy bought the
reactors in 2000 and 2001.
A spokesman for the N.R.C., Neil A. Sheehan, said that nuclear
operators must apply for renewal at least five years before
the license is to expire. The agency then typically takes
two years to grant or deny the license, which in Entergy's
case, would bring the process to 2010. The new cooling system
would then undergo an environmental review, a process that
could take months.
"We've had 30 years of delay," said Warren P. Reiss,
general counsel for Scenic Hudson. "This is the last
ecological insult to the river. There is a remedy that is
known and available, and Entergy should be obliged to implement
it at the soonest possible time."
Entergy says the new cooling system would be so costly to
build — $1.6 billion by its estimate — that it
may opt not to renew its license. Jim Steets, an Entergy spokesman,
said the figure included about $600 million in lost revenues
from a nine-month shutdown of the plant during construction.
"We may or may not apply for it," Mr. Steets said
of the license renewal. "An order to install cooling
towers may preclude it."
But a consultant hired by environmental groups said such
a system would cost far less, $200 million to $360 million,
said David K. Gordon, a senior lawyer for Riverkeeper. And
the groups argue that a long shutdown would not be necessary.
Since the Sept. 11 attacks, Riverkeeper has been a forceful
advocate of Indian Point's closing. While the group says it
is not using fish mortality as another weapon against the
plant, it does acknowledge a link.
"They have no right to kill over a billion fish each
year," said Alex Matthiessen, executive director of Riverkeeper.
"If a new cooling system helps make Entergy's enterprise
unprofitable and forces them to shut down the plant, all the
better.
BACK
TO TOP
|